Construction Is Underway!
7-8-2015
The old library has been knocked down and site preparation is underway. In the next couple of weeks, construction fencing will be installed around the footprint of the new police station. We are excited to get this process underway. We will be keeping the public up to date every step of the way, through social media, and our website. Please check back for additional information.
8-12-2015
This week at the site of the new Millis Police Station, a new 30" drainline will be installed.
12-27-2015
The footings and foundation are almost complete!
2-26-2016
Block wall are being built, and walls are being hoisted into place.